01Red Deer, AB · tier 2 market
High-rise apartment tower cost in Red Deer
A cast-in-place concrete residential tower with underground parking, amenity floors and a formed core. Vertical transportation, crane time and the parking structure are the cost centres that separate a tower from a low-rise.
02The curated band
Hard cost, standard spec
$365/sf
Band $294 – $454
All-in, preset build
$727/sf
220,000 sf, 20 storey
Hard share of all-in
71%
Rest is soft cost, charges, contingency, escalation
AB escalation
4.1%/yr
Quarter ending 2025-09-30
Buildlor Construction Cost Index · Last updated 2026-01-15 · Maintained by Buildlor Cost Desk
Scope: Red Deer, Alberta — High-rise apartment tower
Inputs: Altus Group Canadian Cost Guide 2025, Toronto base range; Statistics Canada Building Construction Price Index, table 18-10-0135-01
Next scheduled review: 2026-04-15
03Build the stack
Your build
All-in cost — Apartment (high-rise), Red Deer
$159,895,258
$727/sf · band $126,562,757 – $202,645,680
At this specification the apartment (high-rise) prices at about $727 per square foot all-in, with a 48% spread between the low and high band. Hard cost is 71% of the total and everything above it is soft cost, charges, contingency and escalation.
| Line | Amount | $/sf |
|---|---|---|
| Substructure and foundations | $12,779,649 | $58/sf |
| Structure and frame | $25,559,297 | $116/sf |
| Envelope, roofing and glazing | $19,169,473 | $87/sf |
| Interior partitions and finishes | $14,909,590 | $68/sf |
| Mechanical and plumbing | $17,039,532 | $77/sf |
| Electrical and life safety | $11,714,678 | $53/sf |
| General conditions and fee | $5,324,854 | $24/sf |
| Site work and servicing | $6,389,824 | $29/sf |
| Hard cost subtotal | $112,886,896 | $513/sf |
| Design and consultants | $9,934,047 | $45/sf |
| Permits, approvals and reviews | $2,483,512 | $11/sf |
| Project management and testing | $4,967,023 | $23/sf |
| Financing, insurance and legal | $7,450,535 | $34/sf |
| Contingency (12%) | $16,526,642 | $75/sf |
| Escalation to midpoint (12 mo) | $5,646,603 | $26/sf |
| All-in cost | $159,895,258 | $727/sf |
How these figures were produced
- Observed — Recorded directly from the cited source series, unadjusted.
- Modelled — Derived arithmetically from observed inputs using the published method; not a market quote.
Carry this deal forward
Your numbers travel with the link
The deal is encoded in the URL, never stored. Open a sister utility and it arrives pre-filled.
- LeaselorLeasing & incomeTurn rent, TMI and vacancy into the NOI you underwrote.Soon
- CapitalorPre-acquisition & financingDebt-service the deal and find the loan the numbers support.
- StratalorLong-term operations & facility managementBenchmark opex and TMI to hold the NOI you underwrote.
Keep this deal under watch
Save the deal and Dealor re-runs it every month against current rates and your own dates — so you hear about a broken DSCR or a lapsing renewal before your lender does.
04What moves the number
Cost drivers for this type in Red Deer
Underground parking levels
each level below grade carries excavation, shoring and dewatering that scale non-linearly.
Formwork cycle
a faster floor cycle reduces general conditions but demands a larger crew and more crane capacity.
Amenity and lobby quality moves the finish package far more than suite finishes do.
Amenity and lobby quality moves the finish package far more than suite finishes do.
Elevator count and speed are set by code and occupancy, not by budget.
Elevator count and speed are set by code and occupancy, not by budget.
Red Deer draws trades from both major Alberta cities, so its pricing tracks whichever market is slower. That is why the same drawings priced in Red Deer and in Toronto do not land at the same number even when the trades are the same.
On the preset build above, hard cost is $112,886,896 and everything after it — soft cost, charges, contingency and escalation — adds $47,008,361. Budgeting off a hard rate alone is the single most common way an early construction budget goes wrong.
Buildlor facts
- Hard cost for a apartment (high-rise) in Red Deer sits at $365 per square foot at standard specification.
- Soft cost at 22% of hard adds $24,835,117 to the preset build.
- AB construction escalation is running at 4.1% a year, or $5,646,603 over twelve months on this build.
05Related
Other types in Red Deer
- Warehouse and distribution shellWarehouse · tier 1 topic
- Low-rise office buildingOffice (low-rise) · tier 1 topic
- Retail strip and plaza shellRetail strip · tier 1 topic
- Low-rise apartment buildingApartment (low-rise) · tier 1 topic
- Office tenant improvementOffice fit-out · tier 1 topic
- Retail tenant improvementRetail fit-out · tier 2 topic
- Medical and dental clinic fit-outMedical fit-out · tier 3 topic
06Questions
What does it cost to build a apartment (high-rise) in Red Deer?
On the curated Red Deer band, hard cost runs $294 to $454 per square foot for a apartment (high-rise) at standard specification. Adding site work, soft cost, charges, contingency and twelve months of escalation puts the all-in figure near $727 per square foot on a 220,000 sf preset. Your own area and specification change that number, which is what the builder above is for.
Why does Red Deer price where it does?
Red Deer draws trades from both major Alberta cities, so its pricing tracks whichever market is slower. The published Toronto base range is scaled by a documented factor of 0.89 for this market, and the AB escalation series is running at 4.1 percent a year.
Is the development charge in this number?
No. We do not yet hold a charge row for Red Deer. Enter the figure from the municipality's schedule in the builder.
What is excluded from every figure here?
Land, financing interest during construction beyond the soft-cost allowance, taxes recoverable as input credits, tenant furniture and equipment, and any remediation or off-site works. Those are separate line items in a real proforma.
07Sources
Sources
- [1] Altus Group Canadian Cost Guide 2025, Toronto base range — Published Toronto range scaled by a documented city cost factor of 0.89. Hard cost only: excludes land, soft costs, development charges and contingency.
- [2] Statistics Canada Building Construction Price Index, table 18-10-0135-01 — Non-residential building construction, Calgary CMA.
Not advice — Buildlor is a data publisher. We do not bid, price, estimate, or build work, and nothing here is a quote, a tender price, or construction advice. Figures are indicative order-of-magnitude benchmarks for early budgeting and must be confirmed by a qualified cost consultant, quantity surveyor, or general contractor before you rely on them. About Buildlor